← Back to selected work

01 / Load forecasting / Utility planning

Dominion Energy load forecast

A probabilistic forecast of data center electricity demand in Dominion Energy Virginia’s territory (PJM DOM zone), 2025–2035, and what serving it means for capital spending, rate base, customer rates and utility earnings.

Decision signalDOMINION / MODEL 01
20252035
12,957 MWMedian new data center peak by 2035 · 90% range 8,661–16,569 MW
Model chart / new data center peak, 90% range13.0 GW by 2035
Dominion Energy Virginia data center peak load forecastThe median forecast of new data center peak demand rises from 0.2 gigawatts in 2025 to 6.6 gigawatts in 2030 and 13.0 gigawatts in 2035. The 90 percent range in 2035 is 8.7 to 16.6 gigawatts.6.6 GW · 203013.0 GW median · 2035 (8.7–16.6 GW)202520302035
median (P50)90% range (P5–P95)MW of new data center peak
Monte Carlo simulation of a probability-weighted pipeline of 46 projects, with shared shocks to build probabilities and timing
$83.4Bbase-case capital to 2035
+10.1%2035 rate effect, base
5.05%peak model holdout MAPE

How much load is coming, and who pays if it doesn’t?

Planners face a two-sided error. Under-building risks reliability shortfalls and emergency procurement; over-building risks stranded assets whose cost falls on every ratepayer. Data center demand arrives in large, lumpy blocks of 100 to 1,000+ MW per campus, runs nearly flat around the clock and is announced years before it is energized, so a single-point forecast hides the risk.

The model treats announced capacity as a probability-weighted pipeline, not a certainty: only the stage-weighted expectation is counted, and the range allows for shared shocks that would hit many projects at once.

From hourly load to a rate impact, in one reproducible pipeline.

Hourly demand and weather give a weather-normalized organic baseline with historical data center load removed. A hand-compiled, stage-tagged project pipeline becomes probabilistic incremental load. That load is translated into accredited capacity, nameplate build by technology, capital, rate base, revenue requirement, rates and earnings, and compared with a no-new-data-center counterfactual.

The pipeline
StepWhat it does
BaselineEIA-930 hourly load for the PJM DOM sub-region (2019–2025) and population-weighted weather. Existing data center load (5,866 MW connected in 2025) is removed before fitting, so growth is not counted twice.
Pipeline46 de-duplicated projects, 17,530 MW of grid capacity, each compiled by hand with a source URL and a verbatim capacity quote, tagged by stage from announced to under construction.
SimulationLow / Base / High scenarios plus a Monte Carlo with a common shock to build probability and timing in every draw.
Capital and ratesAccredited capacity under PJM FPR and ELCC, capital by technology, rate base, revenue requirement, system-average rate and net income.
RiskTornado sensitivity, a stranded-load stress test and a GS-5-style large-load tariff.

Plan to the median, and protect against the downside.

New data center peak and rate effect
ScenarioDC peak 2035 (MW)Capital to 2035Rate effect 2035
Low9,234$58.6B+8.1%
Base13,126$83.4B+10.1%
High17,753$112.8B+12.0%
Monte Carlo median12,957$82.6B+10.3%

Base-case 2035 system peak is 37,013 MW, 8.5% below the PJM 2026 load forecast, and inside the model’s 90% range. The base case raises rate base by $64.7B and annual net income by about $3.3B by 2035. The average rate reaches 15.35 ¢/kWh against 13.93 ¢/kWh in the counterfactual.

The central risk is asymmetric. If 25% of the load the system is built for fails to arrive after 2030, the 2035 rate effect becomes +13.8% with no protection, but +5.3% under a large-load tariff with minimum charges (85% of contracted T&D demand, 60% of generation demand) and 25% upfront customer contribution.
Sensitivity / what moves the 2035 rate effecttornado
Tornado chart of the 2035 rate effect against nine drivers. Data center load factor, energy cost and capital cost swing it the most.
The assumptions that most deserve diligence are data center load factor, marginal energy cost and capital cost.

Tested on years the model had not seen.

The organic baseline is trained through 2023 and evaluated on 2024 onward. The daily peak model reaches a MAPE of 5.05%, against 14.33% for a seasonal-naïve benchmark and 16.77% for a trend-only model; the energy model reaches 4.26%. Annual peak errors on the holdout years are 3.9% (2024) and 3.2% (2025). The report also notes where it falls short: four months show a residual bias, and month indicators are the next refinement.

Stage procurement behind signed service agreements.

Plan generation and transmission to the median forecast, stage procurement with explicit decision gates tied to signed Electric Service Agreements, and condition large-load interconnection on tariff protections that place stranded-cost risk on the customers that create it.

Independent research. Every numeric input is either cited to a public source or labeled an assumption in the report’s Appendix A, and the most influential ones are tested in the sensitivity analysis. Not investment advice.